Two development appraisals can show the same sales value and construction cost while describing different commercial outcomes. The missing variable may be time: when expenditure is incurred, when units complete and when cash becomes available to repay borrowing.

For a developer reviewing a delayed scheme, changing a completion date is therefore more than a programme adjustment. It can alter finance costs, the period of exposure and the relationship between receipts and planning obligations. A financial viability assessment should make those effects visible and explain their causes.

Put the programme inside the appraisal

Start with a delivery sequence that the project team can defend. Record acquisition, mobilisation, infrastructure, construction phases, practical completion and receipt dates. Where affordable housing or commercial space is involved, distinguish the payment assumptions from private housing sales.

Then check which costs are genuinely time-related. Some expenditure may shift with the works; other costs may continue during the delay. Moving every cost and receipt by the same number of months can conceal the pressure on working capital.

A programme should identify dependencies as well as dates. A delayed access agreement, utility connection or pre-commencement matter affects a scheme differently from a slower sales period after construction is complete. The model should reflect the particular mechanism.

Understand what the finance assumption represents

Government viability guidance recognises general finance costs, including loan costs, as part of the assessment. For a particular scheme, identify the borrowing profile, interest assumption, fees and repayment sequence rather than treating finance as an unexplained percentage.

An average borrowing balance can be useful for a quick sense-check, but it is not a substitute for a properly structured cash-flow model where timing is material. Be clear whether interest is calculated on actual monthly balances, whether it compounds and how fees enter the calculation.

It is equally important to reconcile the finance assumption with the treatment of developer return and contingencies. Identify what each allowance is intended to cover, so the report does not count the same risk twice or silently omit it.

A simple six-month illustration

Assume, purely for illustration, that £3 million remains borrowed for an additional six months at 8% simple annual interest. The additional interest is £120,000: £3 million multiplied by 8% multiplied by half a year.

This is not a quotation for development finance or a claim about current market rates. It excludes changing debt balances, compounding, fees, any income and other effects of delay. It shows why unchanged headline sales and build-cost totals do not necessarily mean the commercial position is unchanged.

A full appraisal should replace the simplified assumption with the project's actual or properly evidenced forecast cash movements. It should also test whether part of the expenditure can be deferred, whether receipts can be accelerated and whether a revised sequence changes the overall result.

Read S106 triggers alongside the cash flow

List each obligation, its trigger, indexation basis and payment timing using the actual agreement or proposed terms. A payment linked to commencement can affect the funding requirement differently from a payment linked to a later occupation threshold.

That observation does not establish that a contribution should be reduced or delayed. It identifies a point to examine with the planning and legal team. Where a change is proposed, explain why it is needed, how infrastructure would still be delivered and what the authority would be asked to agree.

Do not assume that a revised project programme changes an existing legal obligation. Any required variation needs the appropriate process, and the developer must understand the operative terms while discussions continue.

Test a small number of meaningful scenarios

Begin with a clearly dated base case. Then change one material variable at a time before testing combined scenarios. A useful set might cover a six-month delay, slower sales absorption, a revised infrastructure sequence and a change in affordable housing receipt timing.

For each scenario, show the effect on peak funding, finance cost, developer return and residual land value. Explain whether the scenario is a central expectation, an identified risk or a deliberately adverse sensitivity. Combining every pessimistic assumption without explaining its likelihood can make the exercise less useful.

Record potential mitigations as well. A smaller first phase, earlier resolution of enabling works or a different payment profile may improve cash flow, but each option needs to be tested against practical delivery and commercial constraints.

Translate the model into a reasoned viability case

Where application-stage viability evidence is justified, NPPF policy DM5 requires evidenced assumptions and an explanation of relevant differences from the plan's viability evidence. A revised spreadsheet alone does not explain why a delay matters or how it should influence the planning judgement.

Bartons provides financial viability and S106 advice alongside developer planning services. We help connect programme, appraisal and negotiation so that a change in commercial circumstances is presented through a clear, proportionate and evidence-led case.

Policy and guidance checked on 26 November 2026. This article concerns England.